Agenda 111 projects cannot be completed within four years – Health Minister
Published . Category: Health.
The Minister of Health says the government’s Agenda 111 hospital projects cannot be completed within four years, citing funding gaps and construction delays. S…
The Minister of Health says the government’s Agenda 111 hospital projects cannot be completed within four years, citing funding gaps and construction delays. Speaking before Parliament’s Health Committee on Thursday, Health Minister Kwabena Mintah Akandoh said only 36 of the 111 district and regional hospitals are between 60% and 90% complete as of April 2026. “At the current pace and with current releases, we cannot finish all 111 facilities in four years. We need to be realistic with timeline…